We use analytics cookies to understand how you use this site and improve our content. See our privacy policy and cookie policy for details.

Calcs.com
Australia

Retrofit and remediation strategies for masonry structures

14 August 2025 · 12:00 AEST · 60 min

Watch recording
Kieran Bisacre-Peters

Kieran Bisacre-Peters

Business Development and Sales Engineer


Python Fixings logo60 min

About this event

Unreinforced masonry buildings carry significant seismic risk under AS 1170.4, and practical retrofit options are often poorly understood in the field. This session covers assessment and remediation approaches for existing masonry structures: anchor selection, helical tie design, and out-of-plane stability checks under earthquake loads. Presented with PYTHON Fixings Australia.

In this webinar we covered

  • Seismic demand calculation for existing masonry under AS 1170.4
  • Out-of-plane stability checks for unreinforced walls per AS 3700
  • Anchor and helical tie selection for different masonry substrates
  • Capacity verification for resin anchors under combined shear and tension
  • Identifying failure modes in unreinforced masonry on site
  • Documentation and certification requirements for remediation work

What Christchurch revealed about masonry retrofits

The 2010-2011 Canterbury earthquake sequence was, as Kieran put it, "the first example of a heavily seismically retrofitted masonry building population being struck by a major seismic event." The results were confronting: retrofitted buildings in some cases performed worse than expected, and a Royal Inquiry traced many failures back to inadequate anchorage systems - not the retrofit concept itself.

The lesson is not that retrofits don't work. Buildings with properly installed concrete shear walls and steel braced frames survived intact a few kilometres from total collapses. The lesson is that design intent and installed performance can diverge sharply when anchor workmanship and substrate condition are not rigorously controlled.

Anchor performance in existing masonry

The University of Auckland's URM anchor study - still the largest of its kind in the world after a decade of research - produced some counterintuitive findings that every engineer specifying into existing masonry should know.

Long, thin anchors outperform short, fat ones. Concrete screw anchors are optimised for concrete: short and large-diameter. In masonry, short anchors engage only one or two brick courses, providing no redundancy. Large diameters (12mm+) increase brick-splitting risk during installation. Best practice is 8-10mm maximum diameter and as long as the substrate will accommodate - engaging multiple courses across the full anchor length.

Bigger is not better for diameter in clay brick. The study found that 20mm anchors can provide less tension capacity than 16mm anchors in clay brick. Larger pilot holes remove more material and shift the failure mode from combined cone-and-pullout to brick-splitting - a more brittle mechanism with less capacity.

The standard US code detail is weaker in masonry. Installing epoxy anchors at 22.5 degrees downward (a detail required in some US standards) is substantially weaker than horizontal installation in masonry substrates. Engineers adapting international detailing to Australian practice should verify this.

Drilling technique directly affects anchor capacity

Using a heavy hammer-action concrete drill in soft masonry causes radial stress fractures and blowouts on the backface of bricks. This can reduce anchor capacity by up to 60 percent compared to the same anchor installed with a light-action or rotary-only masonry drill. The correct tool is a masonry-specific drill with light hammer action or rotary-only mode - not a standard SDS-plus concrete drill.

Parapets: where the codes' assumptions break down

AS 1170.4 allows parapets to be assessed under a rocking mechanism. A critical finding from Canterbury is that DPM (damp-proof membrane) layers at parapet bases create sliding surfaces. Several parapets did not rock as modelled - they slid off the building. Where a DPM is present at the base of a parapet, the rocking assumption is not conservative and the assessment should account for sliding.

Post-Canterbury data also showed significant parapet collapse rates even where steel bracing had been installed. Investigation found the bracing itself was adequate; failures traced back to epoxy anchor failures at the base connections.

Cavity tie corrosion: what visual inspection misses

Australia has no mandatory cavity tie inspection requirement (unlike the US, which requires inspection every 5-10 years). In lime mortar construction - which is common in older Australian commercial and residential stock - the mortar is porous, water accumulates in bed joints, and original flexible wire ties have no corrosion protection.

The deceptive part: borescope inspection may show a tie that looks intact at the exposed end. Removing the adjacent brick can reveal that the tie has completely disintegrated at the point where water contacts it. In any lime mortar building where tie condition is uncertain, assume failure unless a systematic physical inspection has confirmed otherwise.

Timber strongbacks as a practical out-of-plane solution

Timber strongbacks are often overlooked in favour of steel, but they have meaningful practical advantages: lower cost, simpler installation with hand tools only, and modifiability on-site without fabrication lead times. Testing showed equivalent or better performance to steel systems: a 3-metre URM wall with timber strongbacks at 600mm centres sustained approximately 30 percent above the Christchurch earthquake acceleration with no failure.

Q&A

How do you inspect cavity wall ties in an existing building?
Systematic brick extraction at multiple locations is the most reliable method - particularly in lime mortar construction. Borescope inspection can look acceptable at the exposed tie end while the tie has completely corroded where water accumulates in the bed joint. In lime mortar buildings, assume ties are compromised unless a recent physical inspection confirms otherwise.
What anchor diameter performs best in clay brick masonry?
Smaller diameters perform better. 8-10mm maximum is the recommended range for clay brick substrates. The University of Auckland's URM anchor study - still the largest of its kind globally - found that 20mm anchors can provide less tension capacity than 16mm anchors in clay brick, because larger pilot holes remove more material and shift the failure mode from combined cone/pullout to brick-splitting.
Why do helical ties underperform in seismic applications?
Helical ties work by cutting oversized grooves in soft masonry. Under cyclic seismic or wind loading they gradually disengage from those grooves, progressively losing capacity. Kieran described this as a "porcupine effect" - ties popping out under repeated load reversals. A building retrofitted to code spacings with helical ties experienced veneer pull-away during a seismic event. Screw anchors provide substantially better cyclic performance through direct thread-substrate engagement.
Can timber strongbacks be designed for composite action with the masonry wall?
Yes. Both full-load and composite design approaches have been tested and are viable. Composite designs require closer anchor spacing to develop interaction between wall and strongback. Testing showed a 3-metre unreinforced wall with only a diaphragm connection failed at low acceleration; the same wall with timber strongbacks at 600mm centres sustained three times the load - approximately 30 percent above the recorded Christchurch earthquake acceleration.
What are the edge distance requirements for mechanical anchors in masonry?
Minimum 30mm from clay brick edges and 50mm from concrete block edges. For situations close to these limits, statistical approaches or site-specific testing can be used to characterise capacity under uncertainty. AS 3700 spacing standards apply for production installations; closer spacings are required where composite action between veneer and backing is needed.
How do epoxy anchors fail in existing masonry, and how do you prevent it?
The most common failure mode is workmanship, not the epoxy itself. Critical points: insufficient dust removal from pilot holes (vacuum extraction is best practice), too little epoxy in the hole, and loading anchors before full cure. Masonry has low and variable compressive strength, making capacity difficult to verify without destructive testing. Where epoxy anchors are specified, a rigorous QA plan covering installation supervision and pull-testing is essential.
What is the maximum height for a post-tensioned chimney retrofit?
Implementations up to approximately 8 metres have been completed. Post-tensioned rod and plate systems have been tested to sustain approximately 2g - compared to around 0.4g for as-built chimneys. This makes post-tensioning substantially more effective than steel brace systems, which have shown 25 percent failure rates in post-Christchurch observations, often due to epoxy anchor failures at the base rather than brace failures.

Speakers

Kieran Bisacre-Peters, Business Development and Sales Engineer at PYTHON Fixings Australia

Kieran Bisacre-Peters

Business Development and Sales Engineer · PYTHON Fixings Australia

Kieran is a Business Development and Sales Engineer at PYTHON Fixings Australia, working with structural engineers and builders on masonry fixings solutions across commercial, residential, and heritage retrofit projects. He has extensive experience specifying anchor and tie systems for remediation work, including seismic upgrades to existing masonry structures.

Python Fixings logo

Python Fixings supplies specialist masonry anchor and tie systems for new construction, retrofit, and heritage remediation projects across Australia.

https://www.pythonfixings.com.au

Standards referenced

AS 3700AS 1170.4

Make decisions you can defend at review time

Share a calculation with the basis of design attached - inputs, formulas, and code references alongside the result.